Spindle Run-in (Warm-up)

Spindle run-in (warm-up) may be required to stabilize the rotation of the spindle.

Situations Requiring This Work
  • When installing the machine
  • When replacing the spindle unit
  • When the machine has not been used for a prolonged period
  • Before use on days when the ambient temperature is low
Procedure
  1. Close the front cover.

    Gently pull up on the front cover and then lower it until a click is heard.

    DWX-53DC_Cover_Close
  2. Turn on the machine.
    The machine starts the initial operations. When the status light stops flashing and remains steadily lit, the initial operations are complete.
  3. Show VPanel.
  4. Open the Machine settings window.
    1. In the top window of VPanel, select the machine to operate.
      When you have connected multiple machines, you can switch to a different machine to operate by clicking its image under MACHINE STATUS.
    2. Click Icon_VPanel_MachineSetting.

      The Machine settings window is displayed.

      VPanel_Main_MachineSetting
  5. On the Maintenance tab, click ****-****.
    VPanel_MachineSetting_Maintenance_SpindleRun-in
  6. When the window shown in the following figure appears, click OK.

    Start spindle run-in.

    VPanel_Dialog_SpinleRun-in

    When a message indicating that work is complete appears, the spindle run-in is complete.